Management Site Visits

GRIDCo Management Undertakes Project Site Visits (Part II)

By |2024-04-01T20:59:41+00:00March 27th, 2024|News|

As a follow-up to the recent Management Team’s visits to some GRIDCo project sites in the Upper East and Bono Regions, we present an update on two (2) Substations and Transmission Line projects, which GRIDCo is executing in the Kumasi Operational Area in the Ashanti Region.GRIDCo’s 161kV Konongo-Kumasi (J2K) Transmission Line project, which involves the

GRIDCo Management Undertakes Project Site Visits – Newmont Ahafo North and Cardinal Namdini

By |2024-04-01T20:13:48+00:00March 26th, 2024|News|

During Management’s recent tours of GRIDCo’s Operational Areas, they took some time off to undertake site visits to apprise themselves of the progress of works on some ongoing Substation and Transmission Line Projects. The Substation and Transmission Line projects of interest are: • Construction of 161kV HV Powerline and Substation; Newmont Ahafo North, Bono